V4 SPradhan Logbook
From SoftwarePractice.org
Contents |
August 2008
14th August 2008
Work Completed
- Wrote Narrative for Developers
- Investigated SVN Repositories
Difficulties
- Nil
Work to be Done
- Nil
Total Time Spent: 1 Hr
20th August 2008
Work Completed
- Attended Meeting
Difficulties
- Nil
Work to be Done
- Update Narrative
- Put Log Book Online
- Update Quality Attribute Matrix
- Update Introduction
Total Time Spent: 1 Hr
24th August 2008
Work Completed
- Updated Narrative
- Put Log Book Online
- Updated Quality Attribute Matrix
- Updated Introduction
Difficulties
- Nil
Work to be Done
- Nil
Total Time Spent: 1 Hr
28th August 2008
Work Completed
- Attended Meeting
Difficulties
- Nil
Work to be Done
- 2 Usage Narratives
- 2 Use-case maps
- 2 Use-case maps analysis
- Link Log to main page
- Features of Stakeholder
Total Time Spent: 2 Hrs
September 2008
2nd September 2008
Work Completed
- 2 Usage Narratives
- 2 Use-case maps
- 2 Use-case maps analysis
- Link Log to main page
Difficulties
- Nil
Work to be Done
- Features of Stakeholder
Total Time Spent: 2 Hrs
4th September 2008
Work Completed
- Attended Meeting
- Revised Conceptual Architecture
- Execution Architecture
Difficulties
- Nil
Work to be Done
- Features of Stakeholder
- Use Case Maps
- Use Case Map analysis
- Quality Narratives
- Narratives (Personas)
- Key contextual features
- Usage Narratives
Total Time Spent: 2 Hrs
9th September 2008
Work Completed
- Features of Stakeholder
- Quality Narratives
- Key contextual features
- Usage Narratives
Difficulties
- Coming up with good usage narratives
- Finding out what key contextual features meant
Work to be Done
- Use Case Maps
- Use Case Map analysis
- Narratives (Personas)
Total Time Spent: 3 Hrs
10th September 2008
Work Completed
- Use Case Maps
- Use Case Map analysis
Difficulties
- Nil
Work to be Done
- Narratives (Personas)
Total Time Spent: 1 Hr
11th September 2008
Work Completed
- Narratives (Personas)
- Proof Read
- Also done presentation
Difficulties
- Hard to present since no criteria was given whereas we were expected to mark against certain criteria
Work to be Done
- Nil
Total Time Spent: 4.5 Hrs
15th September 2008
Work Completed
- PHP web interface
Difficulties
- Nil
Work to be Done
- Nil
Total Time Spent: 0.5 Hr
18th September 2008
Work Completed
- Configure and demonstrate code
Difficulties
- Nothing notable
Work to be Done
- Nil
Total Time Spent: 2 Hrs
October 2008
11th October 2008
Work Completed
- Write Class
Difficulties
- Nil
Work to be Done
- Read Class
Total Time Spent: 0.5 Hr
12th October 2008
Work Completed
- Read Class
Difficulties
- Wasn't recognising certain packages
Work to be Done
- Nil
Total Time Spent: 1 Hr
16th October 2008
Work Completed
- Nil
Difficulties
- Didnt understand the requirements of milestone 1 (as a team)
Work to be Done
- Incorporate Feedback from Milestone 1
Total Time Spent: 1 Hr
23rd October 2008
Work Completed
- Fixed Key Contextual Factors
Difficulties
- Didn't understand the concept of enablers
Work to be Done
- Fix the rest of milestone 1
Total Time Spent: 1 Hr
30th October 2008
Work Completed
- Formatted Wiki
- Aligned Wiki with Marking Criteria
- Changed Overview
- Added to Narratives/Personas
- Updated Key Contextual Factors
- Added to Quality Narratives
Difficulties
- Nil
Work to be Done
- Work on Conceptual, Execution, Implementation Architectures
Total Time Spent: 4 Hrs
November 2008
4th November 2008
Work Completed
- Added List of Items to Complete
- Put in Effects of Key Contextual Factors on Architecture
- Done Run-time and Life Cycle Events
Difficulties
- What are Run-Time and Life Cycle Events
Work to be Done
- Log Books
- Reflections
- Proof Read
Total Time Spent: 2 Hrs
5th November 2008
Work Completed
- Put handwritten logbook onto wiki
- Finish Reflections
- Proof Read
Difficulties
- Nil
Work to be Done
- Nil
Total Time Spent: 2 Hrs